Project Schedule Management

To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility. What technique is she using ?

Which of the following is true regarding the project charter ?

if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?

A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is \$720,000. The planned budget for this length of the time was \$600,000. He finds that

A project's approved budget is \$250,000 and planned budget to date is \$150,000. What will be the Schedule Variance when Schedule Performer Index is 0.8 ?

Which one of the following takes progressive elaboration approach and plans the work in the near term in detail and future work in a higher level ?

While working with your team members on activity sequencing, a team member identifies that a series of activity sequencing method may be utilized in this situation ?

Which one of the following estimating techniques uses mathematical models based on historical records from other projects and can produce higher levels of accuracy ?

You are overseeing a data center project, the team members have finished creating WBS and WBS dictionary also completed activity sequencing and submitted their activity duration estimates to you. Recently, you developed the project schedule. What should you be focusing on next ?

Which of the following is FALSE about analogous estimating ?