Project Cost Management

  1. A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?

    A Cost Performance Index (CPI) of 0.89 means :

    One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and :

    If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV) ?

    At your project, EV = $130,500 ; PV = $125,000 ; and AC = $129,000. Which one the following statement is true ?

    A project has a BAC = $45,000; PV = $30,000; AC cumulative = $25,000 ; cumulative EV = $24,000. You decided to perform a forecasting analysis and calculated the values for EAC, ETC, and VAC. Which of the following is NOT true ?

    Output of Develop Budget

    Which one of the following is FALSE about TCPI ?

    The rough estimate range was $75,000 to $200,000, and definitive estimate come to be around $150,000 plus 10% additional cost to account for contingency matters. The additional 10% is considered part of

    If CPI is 90%