Focus Area

1. 
Scope change control MUST be integrated with all of the following control processes EXCEPT:

2. 
During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?

3. 
When a product or service completely meets customer's requirements :

4. 
The subprocesses of a project are linked by one subprocess providing an output that feeds one or more subprocesses as an input. Thus, subprocess are defined by PMI as  having an input,________,, and an output.

5. 
 A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?

6. 
When should the Validate Scope process be done ?

7. 
Cost associated with inspection, laboratory measurements and analysis, machinery maintenance and calibration, field-testing, and procedure checking are examples of which of the following ?

8. 
Planning a project is a process that develops products such as a schedule. This process produces the following for a schedule:

9. 
Constructive team roles include:

10. 
A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is \$720,000. The planned budget for this length of the time was \$600,000. He finds that :

11. 
A project was estimated to cost \$1.5 million and scheduled to last six months. After three months, the earned value analysis shows the following: BCWP = \$650,000 BCWS = \$750,000 ACWP = \$800,000 What are the schedule and cost variances?

12. 
Configuration management is any documented procedure used to apply technical administrative direction and surveillance to:

13. 
You are building a water treatment facility. Routine tests reveal that there are contaminants in the water but that they have an extremely low risk for causing any sickness. As the project manager, you should:

14. 
All the following statements about change control are incorrect, EXCEPT :

15. 
To control the schedule, a project manager is reanalyzing the project to predict project  duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility.  What technique is she using ?

16. 
A KEY activity for achieving customer satisfaction is to define:

17. 
The measure used to forecast project cost at completion is:

18. 
What is the difference between the project plan and the performance measurement baseline?

19. 
As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer  requirements. The results should be documented and used for:

20. 
Which one  of the following is NOT a planning process  ?

21. 
An individual's willingness to take a risk can be determined by:

22. 
Conflict resolution techniques that may be used on a project include:

23. 
Risk response development is intended to:

24. 
What is the meaning of Perform Integrated Change Control

25. 
Which of the following is a KEY output of the Validate Scope process ?

26. 
Ideally, communication between the project manager and the project team members should take place:

27. 
A project schedule completion date will change if:

28. 
When it appears that a design error will interfere with meeting  technical performance objectives, the PREFERRED response is to:

29. 
Virtual team is a tool for which of the following processes ?

30. 
While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late  finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?

31. 
A project's payback period ends when:

32. 
You just identified a new external risk during the executing phase that may impact your project positively. What is your first step ?

33. 
The sender-receiver model is a basic model of communication that demonstrates how information is sent from the sender and how it is received by the receiver. This model is designed to assist project managers and team members in improving their communication skills. This communication model highlights mostly on which one of the following ?

34. 
One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and :

35. 
Which of the following assess someone's current engagement level in a project ?

36. 
Which of the following techniques is used to control the project  schedule?

37. 
All of the following will occur during project initiating EXCEPT :

38. 
Which of the following is true regarding the project charter ?

39. 
A scope statement is important because it:

40. 
The objective of fast tracking a project is to:

41. 
Which one of following PMO structure mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs ?

42. 
A contractor's deliverable has been delayed 30 days. The process of determining how this event will affect the project schedule is called risk:

43. 
During project execution, PM/PMO monitors specific results to determine if they comply with relevant standards and identifying ways to eliminate causes of inadequate result is :

44. 
A controlling process is necessary in project management to ensure planned actions are executed and measured for progress. The controlling process for the schedule typically will focus on:

45. 
Which of the following is output of Manage Project Knowledge process ?

46. 
One way that the graphical evaluation and review technique (GERT) differs from the program evaluation and review technique (PERT) is that it:

47. 
The MAJOR processes for project integration management are:

48. 
Project A has net present value (NPV) of \$30,000, will take 5 years to complete, and the associated cost \$10,000.Project B has NPV of \$60,000, will take 3 years to complete, and the associated cost \$15,000. Project C has NPV of \$80,000, will take 4 years to complete, and the associated cost \$40,000. Which project will you pick ?

49. 
In what way does free float (FF) differ from total float (TF)?

50. 
Risk quantification includes:

51. 
A control chart helps the project manager :

52. 
Due to cuts in funding, your project has been terminated. The scope verification process:

53. 
A change control board (CCB) is:

54. 
A likely result of using "compromise" to resolve a two-party conflict is:

55. 
Which document contains the information  that describes how the formal verification and acceptance of the project deliverables will be contained ?

56. 
Two of the types of discretionary dependencies that typically have an effect on the sequencing of the  activities in the schedule are those containing hard logic and  those containing soft logic. An example of a soft logic dependency would be:

57. 
The major processes of project communications management are:

58. 
You have thirteen stakeholders in the construction project that you are overseeing. Your initial study about these stakeholders tells you most of them will actively support your project to be successful, but you have couple of stakeholders who may adversely impact your project. When do you think these stakeholders will have the most influence on your project ?

59. 
Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?

60. 
You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope.  Which document provides this information?