Skip to content
Home
About
Profile
Our Clients
Articles
PM in reality
Risks Handling in a Project
Agile Use Case
Cara menghitung unit price berbasis AHSP
Ujian Sertifikasi PMP 2026
Contoh Ujian PMP 2026
PMI Code of Ethics
Training
Consulting
Project Management
Business & Requirement Analysis
PM Center of Excellence
PMIS
Learning
PMP/CAPM (simplified)
PMP 180
CAPM 150
Refreshers
Puzzles & Flashcards
6 Principles
7 PD – FlipCards
FA Puzzle
PD Puzzle
Kanban
APG
PMBOK
PGPG
Models
Tools
Artifacts
Test You PM
Quiz 10×12
PMBOK Overview & Framework
Project Management Process
Project Integration (Business Dom)
Project Scope (Process Dom)
Project Schedule (Process Dom)
Project Cost Management
Project Quality Management
Project Resources (People Dom)
Project Communication (People Dom)
Project Risk Management
Project Procurement Management
Project Stakeholder (People Dom)
Randomized 60
PMP (medium)
PMP 180
ECO 2026
ECO PMP 1
ECO PMP 2
ECO PMP 3
Misc
MSP
Latihan 1
Latihan 2
Latihan Akhir
MSP – 1
MSP Intro (1) – 12
MSP Intro (2) – 12
MSP Intro (3) – 6
MSP Intro (4) – 2
MSP File Options – 7
MSP View Table – 4
MSP Calendars & Project Info – 10
MSP Change Working Time – 10
Task Info & Predecessors – 8
Predecesors – 9
Network Diagram & CPM – 10
Tracking Gantt, Late Tasks, Status date – 8
MSP – 2
MSP Resource – Type/Rate – 15
MSP Baseline – 15
MSP Cost Non Budget – 10
Project Budget Column
MSP S-Curve – 15
MSP Reports – 10
MSP Overallocated – Levelling Strategy – 8
Earned Value Management
Konsep EVA pada PMBOK dan Microsoft Project
MSP Custom Fields – WBS – 11
Articles
MSP Multiple Project – Resource Pool – 11
Plan vs Actual %
Trik membuat kolom bobot
Kanban Board
Formulas
Comm Channel
BCR
BEP
IRR
NPV
PBP
ROI
StdDev for CP
Regression
Feedback
DT101
EDIPT Stages
Emphaty
Define
Ideate
Prototype
Testing
Softskills
Herzberg
Maslow
MBTI
Pink’s thoery
TwoTeamGames
Simple Case
Emy’s Test
Home
About
Profile
Our Clients
Articles
PM in reality
Risks Handling in a Project
Agile Use Case
Cara menghitung unit price berbasis AHSP
Ujian Sertifikasi PMP 2026
Contoh Ujian PMP 2026
PMI Code of Ethics
Training
Consulting
Project Management
Business & Requirement Analysis
PM Center of Excellence
PMIS
Learning
PMP/CAPM (simplified)
PMP 180
CAPM 150
Refreshers
Puzzles & Flashcards
6 Principles
7 PD – FlipCards
FA Puzzle
PD Puzzle
Kanban
APG
PMBOK
PGPG
Models
Tools
Artifacts
Test You PM
Quiz 10×12
PMBOK Overview & Framework
Project Management Process
Project Integration (Business Dom)
Project Scope (Process Dom)
Project Schedule (Process Dom)
Project Cost Management
Project Quality Management
Project Resources (People Dom)
Project Communication (People Dom)
Project Risk Management
Project Procurement Management
Project Stakeholder (People Dom)
Randomized 60
PMP (medium)
PMP 180
ECO 2026
ECO PMP 1
ECO PMP 2
ECO PMP 3
Misc
MSP
Latihan 1
Latihan 2
Latihan Akhir
MSP – 1
MSP Intro (1) – 12
MSP Intro (2) – 12
MSP Intro (3) – 6
MSP Intro (4) – 2
MSP File Options – 7
MSP View Table – 4
MSP Calendars & Project Info – 10
MSP Change Working Time – 10
Task Info & Predecessors – 8
Predecesors – 9
Network Diagram & CPM – 10
Tracking Gantt, Late Tasks, Status date – 8
MSP – 2
MSP Resource – Type/Rate – 15
MSP Baseline – 15
MSP Cost Non Budget – 10
Project Budget Column
MSP S-Curve – 15
MSP Reports – 10
MSP Overallocated – Levelling Strategy – 8
Earned Value Management
Konsep EVA pada PMBOK dan Microsoft Project
MSP Custom Fields – WBS – 11
Articles
MSP Multiple Project – Resource Pool – 11
Plan vs Actual %
Trik membuat kolom bobot
Kanban Board
Formulas
Comm Channel
BCR
BEP
IRR
NPV
PBP
ROI
StdDev for CP
Regression
Feedback
DT101
EDIPT Stages
Emphaty
Define
Ideate
Prototype
Testing
Softskills
Herzberg
Maslow
MBTI
Pink’s thoery
TwoTeamGames
Simple Case
Emy’s Test
Focus Area
1.
Scope change control MUST be integrated with all of the following control processes EXCEPT:
Cost
Quality
Procurement
Schedule
None
2.
During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?
Scope Management Plan
WBS Dictionary
Activity List
Project Scope Statement
None
3.
When a product or service completely meets customer's requirements :
The customer pays the minimum price
The cost of quality is low
The cost of quality is high
Quality is achieved
None
4.
The subprocesses of a project are linked by one subprocess providing an output that feeds one or more subprocesses as an input. Thus, subprocess are defined by PMI as having an input,________,, and an output.
Formatting and creation
Tools and techniques
Resolution and action
Process integration
None
5.
A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?
The project is making faster progress and costing more than planned
The project is making faster progress and costing less than planned
The project is making slower progress and costing less than planned
The project is making slower progress and costing more than planned
None
6.
When should the Validate Scope process be done ?
At the end of the project
At the beginning of the project
At the end of each phase of the project
During the planning process
None
7.
Cost associated with inspection, laboratory measurements and analysis, machinery maintenance and calibration, field-testing, and procedure checking are examples of which of the following ?
Opportunity costs
Prevention costs
Sunk costs
Appraisal costs
None
8.
Planning a project is a process that develops products such as a schedule. This process produces the following for a schedule:
Activity definition, activity sequencing, activity execution, and activity duration.
Activity definition, activity sequencing, and activity duration estimating.
Activity identification, activity execution, and activity results.
Activity identification, activity sequencing, activity connection, and activity duration.
None
9.
Constructive team roles include:
Summarizer, recognition seeker, and information seeker.
Information giver, devil's advocate, and clarifier.
Withdrawer, harmonizer, and blocker.
Encourager, initiator, and gatekeeper.
None
10.
A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is \$720,000. The planned budget for this length of the time was \$600,000. He finds that :
The project is on track
The project is ahead of schedule
There is not enough information to determine how the project is doing
The project is over-budget
None
11.
A project was estimated to cost \$1.5 million and scheduled to last six months. After three months, the earned value analysis shows the following: BCWP = \$650,000 BCWS = \$750,000 ACWP = \$800,000 What are the schedule and cost variances?
SV= +\$100,000 / CV= +\$150,000
SV= -\$50,000 / CV= +\$150,000
SV= -\$100,000 / CV= -\$150,000
SV= +\$150,000 / CV= -\$100,000
None
12.
Configuration management is any documented procedure used to apply technical administrative direction and surveillance to:
Control cost increases.
Test new systems against.
Identify and correct problems arising in functional areas of project implementation.
Identify and document characteristics of a product or service
None
13.
You are building a water treatment facility. Routine tests reveal that there are contaminants in the water but that they have an extremely low risk for causing any sickness. As the project manager, you should:
Educate the public about the advances on water treatment technology and the industry efficiency and safety record.
Inform the public that a detailed examination has been ordered to determine the extent to which the problem exists.
Do nothing because there is extremely low risk for sickness except for some effects on small children and the elderly.
Tell the public there is no problem, except for small children and the elderly who need to boil the water before drinking.
None
14.
All the following statements about change control are incorrect, EXCEPT :
A fixed price contract will minimize the need for change control.
Changes seldom provide real benefits to the project.
More detailed specifications eliminate the causes of changes.
Contracts should include procedures to accommodate changes.
None
15.
To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility. What technique is she using ?
Critical path method
Precedence diagramming
Work breakdown structure
Flowchart
None
16.
A KEY activity for achieving customer satisfaction is to define:
Product specificity.
Change control.
The business use.
Requirements
None
17.
The measure used to forecast project cost at completion is:
ACWP
BCWP
SPI
EAC
None
18.
What is the difference between the project plan and the performance measurement baseline?
The project plan usually changes overtime, while the performance measurement baselines generally changed only in response to an approved scope change.
There Is no difference. They are synonymous terms.
The project plan consists of a list of tasks, assignments, and estimates formulated into a network diagram or Gantl chart, while the performance measurement baseline document contains the project plan plus descriptions of approach, scope, and risks.
The project plan is the informal document that is followed by the approved performance measurement baseline document.
None
19.
As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for:
Changing the project scope.
Validating the quality process.
Estimating future projects.
Defining future project tasks.
None
20.
Which one of the following is NOT a planning process ?
Perform Qualitative Risk Analysis
Estimate Costs
Develop Project Team
Create WBS
None
21.
An individual's willingness to take a risk can be determined by:
Decision tree modeling.
Sensitivity analysis.
Utility function.
Monte Carlo method.
None
22.
Conflict resolution techniques that may be used on a project include:
Confronting, compromising, smoothing, and directing.
Controlling, forcing, smoothing, and withdrawing.
Withdrawing, compromising, controlling, and forcing.
Smoothing, confronting, forcing, and withdrawing.
None
23.
Risk response development is intended to:
Construct a list of previous project risks.
Create steps to identify project risks.
Formulate strategies for dealing with adverse events.
Develop measurements to quantify project risks.
None
24.
What is the meaning of Perform Integrated Change Control
Inviting Change Control Board to evaluate, analyse, approve/reject change requests
Reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and the project management plan
Applying agile principles to accommodate changes
The process of preparing, updating and informing change log
None
25.
Which of the following is a KEY output of the Validate Scope process ?
An improved project management information system
A more complete scope management plan
Customer acceptance of project deliverables
Improved schedule estimates
None
26.
Ideally, communication between the project manager and the project team members should take place:
Through the formal chain of command.
Through approved documented forms.
By written and oral communication.
Via daily status reports.
None
27.
A project schedule completion date will change if:
The critical path is reduced.
The contingency is no longer available.
Project resources are reduced.
No float time is available.
None
28.
When it appears that a design error will interfere with meeting technical performance objectives, the PREFERRED response is to:
Develop alternative solutions to the problem.
Decrease the performance value to equal the assessed value.
Reduce the overall technical complexity of the project.
Increase the specified value to set a new performance goal.
None
29.
Virtual team is a tool for which of the following processes ?
Manage team
Develop resource plan
Control resources
Acquire team
None
30.
While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?
This activity will delay the project
The successor activity will be delayed
This activity has a lag
This activity will most probably not delay the project
None
31.
A project's payback period ends when:
Monthly revenue exceeds monthly costs.
Unit profit is realized.
Cumulative revenue equals cumulative costs.
Profit maximum is realized.
None
32.
You just identified a new external risk during the executing phase that may impact your project positively. What is your first step ?
Update the Risk Breakdown Structure
Develop a Risk Response and assign a Risk Owner
Perform Qualitative Risk Analysis
Implement a Risk Response
None
33.
The sender-receiver model is a basic model of communication that demonstrates how information is sent from the sender and how it is received by the receiver. This model is designed to assist project managers and team members in improving their communication skills. This communication model highlights mostly on which one of the following ?
Verbal and nonverbal communication
Noise and feedback loops
Horizontal communication
Communication methods
None
34.
One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and :
Divide by CPI
Multiply by CPI
Multiply by SPI
Divide by SPI
None
35.
Which of the following assess someone's current engagement level in a project ?
Stakeholder Engagement matrix
Stakeholder Register
Salience Model
Power / Interest Grid
None
36.
Which of the following techniques is used to control the project schedule?
Parametric modeling
Performance measurement
Pareto diagram
Statistical sampling
None
37.
All of the following will occur during project initiating EXCEPT :
Identification of internal and external stakeholders.
Assignment of the project manager to lead a project
Development and review of the business case and a feasibility study.
Creation of a project scope statement
None
38.
Which of the following is true regarding the project charter ?
The project charter should be published under the name of a manager external to the project.
The project charter should be published under the project sponsor's name
The project charter should be published under the name of the project champion
The project charter should be published under the name of the project manager.
None
39.
A scope statement is important because it:
Provides criteria for measuring project cost.
Approves the project for the stakeholders.
Provides the basis for making future project decisions.
Provides a brief summary of the project.
None
40.
The objective of fast tracking a project is to:
Increase productivity.
Reduce project duration.
Increase schedule tracking controls.
Reduce project risks.
None
41.
Which one of following PMO structure mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs ?
Directive
Controlling
Constructive
Supportive
None
42.
A contractor's deliverable has been delayed 30 days. The process of determining how this event will affect the project schedule is called risk:
Simulation
Identification
Assessment
Mitigation
None
43.
During project execution, PM/PMO monitors specific results to determine if they comply with relevant standards and identifying ways to eliminate causes of inadequate result is :
Quality Control
Manage quality
Quality planning
Quality management
None
44.
A controlling process is necessary in project management to ensure planned actions are executed and measured for progress. The controlling process for the schedule typically will focus on:
Activities only on the critical path.
Activities starting later than scheduled.
Activities that vary from the plan, whether late or early.
Activities starting earlier than scheduled.
None
45.
Which of the following is output of Manage Project Knowledge process ?
Work performance reports
Approved change request
Work performance data
Lesson learned registers
None
46.
One way that the graphical evaluation and review technique (GERT) differs from the program evaluation and review technique (PERT) is that it:
Represents the duration of the project activities in a probabilistic fashion.
Represents the project baseline chart in a superimposed fashion over both the logic diagram and the Gantt charts.
Uses object oriented programming techniques to allow resources histograms that are attached to the projects Gantt charts.
Allows the relationships in the logic diagram to contain loops.
None
47.
The MAJOR processes for project integration management are:
Project plan development, project plan execution, and scope change control.
Project plan development, project plan execution, and integrated change control.
Project plan development, overall change control, and scope change control.
Project plan development, initiation, and integrated change control.
None
48.
Project A has net present value (NPV) of \$30,000, will take 5 years to complete, and the associated cost \$10,000.Project B has NPV of \$60,000, will take 3 years to complete, and the associated cost \$15,000. Project C has NPV of \$80,000, will take 4 years to complete, and the associated cost \$40,000. Which project will you pick ?
Project C
Project A
Project B
They all have the same value
None
49.
In what way does free float (FF) differ from total float (TF)?
Free float is the amount of total float that does not affect the end date, whereas total float is the accumulated amount of free float.
There is no difference, the two terms are functionally equivalent.
Free float is commonly referred to as slack time, whereas total float is commonly referred to as float time.
Free float only affects the early start of any immediately following activities.
None
50.
Risk quantification includes:
Identifying potential events and impact.
Developing contingency plans and resources.
Enumerating sources of internal and external events.
Evaluating probability and impact.
None
51.
A control chart helps the project manager :
Focus on stimulating thinking
Determine if a process is functioning within set limits
Explore a desired future outcome
Focus the most critical issues to improve quality
None
52.
Due to cuts in funding, your project has been terminated. The scope verification process:
Should be delayed until the project is completed.
Will form the basis of the project audit.
Should be established to document the level and extent of completion.
Should determine the correctness of the work results.
None
53.
A change control board (CCB) is:
An informal or formal group of team members responsible for changes to a project.
An informal group that has oversight of project implementation.
A formally constituted group of stakeholders responsible for ensuring that only a minimal amount of changes occur on the project.
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.
None
54.
A likely result of using "compromise" to resolve a two-party conflict is:
Lose-win.
Win-win.
Win-lose.
Lose-lose.
None
55.
Which document contains the information that describes how the formal verification and acceptance of the project deliverables will be contained ?
Scope verification documents
Statement of work
Communication management plan
Scope Management Plan
None
56.
Two of the types of discretionary dependencies that typically have an effect on the sequencing of the activities in the schedule are those containing hard logic and those containing soft logic. An example of a soft logic dependency would be:
Project A, the company‟s participation in a Pump Industry trade show, depends on the successful completion of Project B, which is building the prototype pump that is going to be displayed.
For the shrink-wrapping on the finished box of software to depend on enclosing the manual and software first.
To install the plumbing and electrical work at the same time on a single family dwelling.
To schedule all unloading of equipment weighing in excess of 50 tons because the daily rent on the crane with that lifting capability is \$10,000.
None
57.
The major processes of project communications management are:
Communications planning, response planning, progress reporting, and information distribution.
Communications planning, information distribution, performance reporting, and administrative closure.
Communication requirements, information distribution, performance reporting, and administrative procedures.
Communications planning, information distribution, schedule reporting, and stakeholder analysis.
None
58.
You have thirteen stakeholders in the construction project that you are overseeing. Your initial study about these stakeholders tells you most of them will actively support your project to be successful, but you have couple of stakeholders who may adversely impact your project. When do you think these stakeholders will have the most influence on your project ?
At the completion of the project.
During executing and monitoring & controlling process group
At the beginning of the project
Throughout the project life cycle
None
59.
Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?
Controlling
Constructive
Supportive
Directive
None
60.
You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. Which document provides this information?
Project charter
Client organization chart
Change control plan
Resource assignment matrix
None