Skip to content
Home
About
Profile
Our Clients
Articles
PM in reality
Risks Handling in a Project
Agile Use Case
Peran AI dalam Manajemen Proyek
Training
Consulting
Project Management
Business & Requirement Analysis
PM Center of Excellence
PMIS
Learning
PMP/CAPM (simplified)
PMP 180
CAPM 150
Refreshers
Puzzles & Flashcards
12 Principles
8 PD – FlipCards
PG Puzzle
PD Puzzle
Kanban
APG
PMBOK7
PGPG
Models
Methods
Artifacts
PG Quiz 10×12
PMBOK Overview & Framework
Project Management Process
Project Integration Management
Project Scope Management
Project Schedule Management
Project Cost Management
Project Quality Management
Project Resources Management
Project Communication
Project Risk Management
Project Procurement Management
Project Stakeholder Management
Randomized 60
PMP (medium)
PMP 180
ECO 2024
ECO PMP 1
ECO PMP 2
ECO PMP 3
Misc
MSP
Latihan 1
Latihan 2
Latihan Akhir
MSP – 1
MSP Intro (1) – 12
MSP Intro (2) – 12
MSP Intro (3) – 6
MSP Intro (4) – 2
MSP File Options – 7
MSP View Table – 4
MSP Calendars & Project Info – 10
MSP Change Working Time – 10
Task Info & Predecessors – 8
Predecesors – 9
Network Diagram & CPM – 10
Tracking Gantt, Late Tasks, Status date – 8
MSP – 2
MSP Resource – Type/Rate – 15
MSP Baseline – 15
MSP Cost Non Budget – 10
MSP S-Curve – 15
MSP Reports – 10
MSP Overallocated – Levelling Strategy – 8
Earned Value Management
Konsep EVA pada PMBOK dan Microsoft Project
MSP Custom Fields – WBS – 11
Articles
MSP Multiple Project – Resource Pool – 11
Formulas
Comm Channel
BCR
BEP
IRR
NPV
PBP
ROI
StdDev for CP
Softskills
Herzberg
Maslow
MBTI
Pink’s thoery
TwoTeamGames
Simple Case
Feedback
DT101
EDIPT Stages
Emphaty
Define
Ideate
Prototype
Testing
Home
About
Profile
Our Clients
Articles
PM in reality
Risks Handling in a Project
Agile Use Case
Peran AI dalam Manajemen Proyek
Training
Consulting
Project Management
Business & Requirement Analysis
PM Center of Excellence
PMIS
Learning
PMP/CAPM (simplified)
PMP 180
CAPM 150
Refreshers
Puzzles & Flashcards
12 Principles
8 PD – FlipCards
PG Puzzle
PD Puzzle
Kanban
APG
PMBOK7
PGPG
Models
Methods
Artifacts
PG Quiz 10×12
PMBOK Overview & Framework
Project Management Process
Project Integration Management
Project Scope Management
Project Schedule Management
Project Cost Management
Project Quality Management
Project Resources Management
Project Communication
Project Risk Management
Project Procurement Management
Project Stakeholder Management
Randomized 60
PMP (medium)
PMP 180
ECO 2024
ECO PMP 1
ECO PMP 2
ECO PMP 3
Misc
MSP
Latihan 1
Latihan 2
Latihan Akhir
MSP – 1
MSP Intro (1) – 12
MSP Intro (2) – 12
MSP Intro (3) – 6
MSP Intro (4) – 2
MSP File Options – 7
MSP View Table – 4
MSP Calendars & Project Info – 10
MSP Change Working Time – 10
Task Info & Predecessors – 8
Predecesors – 9
Network Diagram & CPM – 10
Tracking Gantt, Late Tasks, Status date – 8
MSP – 2
MSP Resource – Type/Rate – 15
MSP Baseline – 15
MSP Cost Non Budget – 10
MSP S-Curve – 15
MSP Reports – 10
MSP Overallocated – Levelling Strategy – 8
Earned Value Management
Konsep EVA pada PMBOK dan Microsoft Project
MSP Custom Fields – WBS – 11
Articles
MSP Multiple Project – Resource Pool – 11
Formulas
Comm Channel
BCR
BEP
IRR
NPV
PBP
ROI
StdDev for CP
Softskills
Herzberg
Maslow
MBTI
Pink’s thoery
TwoTeamGames
Simple Case
Feedback
DT101
EDIPT Stages
Emphaty
Define
Ideate
Prototype
Testing
Random Process Groups
1.
During project execution, PM/PMO monitors specific results to determine if they comply with relevant standards and identifying ways to eliminate causes of inadequate result is :
Quality planning
Manage quality
Quality Control
Quality management
None
2.
Which one of the following is NOT a planning process ?
Perform Qualitative Risk Analysis
Create WBS
Estimate Costs
Develop Project Team
None
3.
The disorientation experienced by people who suddenly find themselves living and working in a different environment is known as:
Sociocentrism
Ethnocentrism
Temporal shock.
Culture shock.
None
4.
A KEY activity for achieving customer satisfaction is to define:
Requirements
The business use.
Change control.
Product specificity.
None
5.
Which of the following is NOT a typical characteristic of a project management office (PMO) ?
Defining and maintaining vendor engagement processes.
Developing and managing project management methodology and standards
Managing project resources and assigning project tasks
Coaching and training project managers.
None
6.
A precise description of a deliverable is called a:
Specification.
Work package.
Baseline.
Work breakdown structure element.
None
7.
Which of the following assess someone's current engagement level in a project ?
Stakeholder Engagement matrix
Power / Interest Grid
Stakeholder Register
Salience Model
None
8.
You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. Which document provides this information?
Change control plan
Project charter
Client organization chart
Resource assignment matrix
None
9.
A scope statement is important because it:
Approves the project for the stakeholders.
Provides criteria for measuring project cost.
Provides the basis for making future project decisions.
Provides a brief summary of the project.
None
10.
All of the following should be done during the closing process group EXCEPT :
Final version of the lessons learned are compiled and made available for future projects.
Completed project deliverables are handed off to operations and maintenance.
Formal sign-off and formal acceptance are received from the customers.
Customer acceptance criteria are determined.
None
11.
A control chart helps the project manager :
Focus the most critical issues to improve quality
Focus on stimulating thinking
Explore a desired future outcome
Determine if a process is functioning within set limits
None
12.
When should the Validate Scope process be done ?
At the beginning of the project
At the end of the project
At the end of each phase of the project
During the planning process
None
13.
While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?
This activity will most probably not delay the project
This activity will delay the project
This activity has a lag
The successor activity will be delayed
None
14.
Which of the following is output of Manage Project Knowledge process ?
Work performance data
Work performance reports
Lesson learned registers
Approved change request
None
15.
All of the following will occur during project initiating EXCEPT :
Assignment of the project manager to lead a project
Creation of a project scope statement
Identification of internal and external stakeholders.
Development and review of the business case and a feasibility study.
None
16.
Pareto analysis, cause and effect, and flow charts are all tools used in quality:
Verification
Planning
Benchmarking
Control
None
17.
A project manager has six stakeholders during requirement gathering phase but the number increase to eleven in the design phase. How many additional channels communication were added at design phase ?
55
45
15
40
None
18.
Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider:
Utilizing the critical chair resources.
Performing resource leveling.
Crashing the schedule.
Conducting reverse resource allocation scheduling.
None
19.
Which of the following are frequently used tools in procurement planning?
Contract type selection, bidders conferences, and expert judgement
Make or buy analysis, expert judgement, and contract type selection
Expert judgement, audits, and bidders conferences
Make or buy analysis, contract type selection, and weighting system
None
20.
Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?
Directive
Constructive
Supportive
Controlling
None
21.
A project manager has a problem with a team member's performance. What is the BEST form of communication for addressing this problem ?
Informal verbal communication
Informal written communication
Formal verbal communication
Formal written communication
None
22.
You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making \$120,000, a 45 percent probability losing \$55,000. What does \$41,250 represent in this case ?
Expected monetary value (EMV)
Net present value
Return of Investment (ROI)
Economic value added (EVA)
None
23.
A project management professional can compare earned value performance data to all of the following project management tools EXCEPT:
Forecasted final costs and schedule estimates.
Critical path analysis.
Technical performance metrics.
Risk mitigation plans.
None
24.
Which one of following PMO structure mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs ?
Directive
Controlling
Constructive
Supportive
None
25.
The sender-receiver model is a basic model of communication that demonstrates how information is sent from the sender and how it is received by the receiver. This model is designed to assist project managers and team members in improving their communication skills. This communication model highlights mostly on which one of the following ?
Communication methods
Verbal and nonverbal communication
Noise and feedback loops
Horizontal communication
None
26.
You are managing a group of related or unrelated projects or programs and other work and achieve specific strategic business objectives and goals. You are a................
Program Manager
Portfolio Manager
Program owner
Project manager
None
27.
In a fixed price incentive fee contract, the target cost is estimated at \$250,000 and the fee at \$35,000. The actual cost came to be \$210,000, since there was a cost saving, the seller shares the saving at a 70/30 ratio ( 70% to the buyer and 30% to the seller). What the final fee and final price ?
\$35,000 and \$210,000
\$47,000 and \$257,000
\$47,000 and \$210,000
\$35,000 and \$257,000
None
28.
Planning a project is a process that develops products such as a schedule. This process produces the following for a schedule:
Activity identification, activity execution, and activity results.
Activity identification, activity sequencing, activity connection, and activity duration.
Activity definition, activity sequencing, activity execution, and activity duration.
Activity definition, activity sequencing, and activity duration estimating.
None
29.
A project loses a contractor in the middle of a project. A new project team is formed to replace the role of the lost contractor and his/her team. As a project manager, what is the FIRST topic to address to the team in the kick-off meeting?
Discuss cost estimates.
Emphasize your authority.
Review detailed schedule.
Identify team roles and responsibilities.
None
30.
A process is a series of actions to bring about a result. In a project, the five basic process groups (PG) are:
Planning, executing, directing, closing, and delivering.
Planning, executing, monitoring, redirecting, and closing.
Initiating, planning, executing, controlling, and closing.
Planning, checking, directing, monitoring, and recording.
None
31.
You are considering the idea of putting all team member in the same physical location for the first time. All of the following is true about colocation, reporting structure, and other items. Which of the following is not true about co-location ?
The goal is to enhance team member's ability to perform as a team
The purpose is to save project budget
It is also call a war room
It is meant to quickly identify concerns and issues and to come up with mutually agreed-upon solution.
None
32.
A change control board (CCB) is:
An informal group that has oversight of project implementation.
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.
A formally constituted group of stakeholders responsible for ensuring that only a minimal amount of changes occur on the project.
An informal or formal group of team members responsible for changes to a project.
None
33.
All the following statements about change control are incorrect, EXCEPT :
More detailed specifications eliminate the causes of changes.
Contracts should include procedures to accommodate changes.
Changes seldom provide real benefits to the project.
A fixed price contract will minimize the need for change control.
None
34.
A project had a list of identified risks. This list was the risks register. Where can one find the high-level risk ?
Project Management plan
Risk Register
Risk Management Plan
Project Charter
None
35.
Sometimes a project coordinator is an assigned role of organization. which of the following statements is NOT true for a project coordinator ?
A project coordinator is weaker than a project expeditor.
A project coordinator is weaker than a project manager
A project coordinator may have some authority in assigning resources.
A project coordinator is not allowed to make budget decisions or overall project decisions.
None
36.
An individual's willingness to take a risk can be determined by:
Utility function.
Sensitivity analysis.
Decision tree modeling.
Monte Carlo method.
None
37.
To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility. What technique is she using ?
Flowchart
Work breakdown structure
Precedence diagramming
Critical path method
None
38.
Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:
Development phase.
Close-down phase.
Concept phase.
Execution phase.
None
39.
A project schedule completion date will change if:
No float time is available.
The critical path is reduced.
Project resources are reduced.
The contingency is no longer available.
None
40.
A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?
The project is making slower progress and costing less than planned
The project is making slower progress and costing more than planned
The project is making faster progress and costing less than planned
The project is making faster progress and costing more than planned
None
41.
You have thirteen stakeholders in the construction project that you are overseeing. Your initial study about these stakeholders tells you most of them will actively support your project to be successful, but you have couple of stakeholders who may adversely impact your project. When do you think these stakeholders will have the most influence on your project ?
At the beginning of the project
During executing and monitoring & controlling process group
At the completion of the project.
Throughout the project life cycle
None
42.
A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is \$720,000. The planned budget for this length of the time was \$600,000. He finds that :
There is not enough information to determine how the project is doing
The project is ahead of schedule
The project is on track
The project is over-budget
None
43.
The MOST common cause of conflict on a project are schedules, project priorities, and :
Resources
Personality
Management
Cost
None
44.
All the following statements concerning procurement documents are incorrect, EXCEPT :
Well-designed procurement documents do not include a procurement statement of work
Procurement documents must be rigorous with no flexibility to allow consideration of seller suggestions.
In general, procurement documents should not include selection criteria
Well-designed procurement documents can simplify comparison of responses.
None
45.
Effective stakeholder management includes all of the following project elements EXCEPT:
Scope change control.
Frequent cost reports.
Timely status information.
Clear requirements definition.
None
46.
What is the MOST effective process to ensure that cultural and ethical differences do not impede success of your multi-national project?
Forming
Training
Co-locating
Teaming
None
47.
During the contract close-out, the project manager needs to document the:
Formal acceptance.
Change control procedure.
Statement of work.
Payment schedule.
None
48.
The subprocesses of a project are linked by one subprocess providing an output that feeds one or more subprocesses as an input. Thus, subprocess are defined by PMI as having an input,________,, and an output.
Formatting and creation
Resolution and action
Process integration
Tools and techniques
None
49.
Which document contains the information that describes how the formal verification and acceptance of the project deliverables will be contained ?
Scope Management Plan
Statement of work
Scope verification documents
Communication management plan
None
50.
You reviewed the WBS and an activity must be completed that your team may not have the expertise to accomplish. You find another team who is willing to take on the work and do the job. What risk response did you use ?
Acceptance
Transference
Mitigation
Avoidance
None
51.
Which of the following is NOT a tool used to manage the stakeholder engagement ?Communication skills
Interpersonal skills
Issue Log
Communication skills
Ground Rules
None
52.
Virtual team is a tool for which of the following processes ?
Develop resource plan
Control resources
Manage team
Acquire team
None
53.
Negotiating across international cultures involves mutual interdependence between parties. The negotiating MUST be conducted in
Generalities and vagueness
Mutual trust and cooperation
Sincerity and compassion
Uncertainty and caution
None
54.
The major processes of project communications management are:
Communications planning, information distribution, schedule reporting, and stakeholder analysis.
Communications planning, information distribution, performance reporting, and administrative closure.
Communication requirements, information distribution, performance reporting, and administrative procedures.
Communications planning, response planning, progress reporting, and information distribution.
None
55.
if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?
1.3
3
6
1
None
56.
A likely result of using "compromise" to resolve a two-party conflict is:
Win-win.
Win-lose.
Lose-win.
Lose-lose.
None
57.
When a project manager places a purchase order for a piece of equipment, it represents which of the following?
Commitment
Capital investment
Expense
Cash out-flow
None
58.
The objective of fast tracking a project is to:
Reduce project duration.
Increase productivity.
Reduce project risks.
Increase schedule tracking controls.
None
59.
The primary purpose of the stakeholder register is :
To record stakeholder issues on the project
To serve as project directory
To keep a list of all project stakeholders.
To map functional requirements back to the originating stakeholder
None
60.
The decomposition process is a technique used to construct a:
Precedence network.
Critical Path Method Diagram.
Work breakdown structure.
Variance analysis.
None