Random CAPM/PMP

Welcome to your Random CAPM/PMP

1. 
A project had a list of identified risks. This list was the risks register. Where can one find the high-level risk ?

2. 
The decomposition process is a technique used to construct a:

3. 
Which of the following is driven by the organization's risk tolerance ?

4. 
Which one of the following is NOT true about a cost reimbursable contract ?

5. 
You are building a water treatment facility. Routine tests reveal that there are contaminants in the water but that they have an extremely low risk for causing any sickness. As the project manager, you should:

6. 
Conflict resolution techniques that may be used on a project include:

7. 
The MOST common cause of conflict on a project are schedules, project priorities, and :

8. 
Which one of the following are the unapproved and undocumented changes and what occurs when to the scope are not detected early enough or are not managed ?

9. 
Which one of the following is FALSE about change management in a project ?

10. 
During project execution, PM/PMO monitors specific results to determine if they comply with relevant standards and identifying ways to eliminate causes of inadequate result is :

11. 
A project was estimated to cost \$1.5 million and scheduled to last six months. After three months, the earned value analysis shows the following: BCWP = \$650,000 BCWS = \$750,000 ACWP = \$800,000 What are the schedule and cost variances?

12. 
A scope statement is important because it:

13. 
As project manager, Henry is cognizant of the importance of effective communication, and he always makes sure that he has the proper physical mannerism, such as facial expressions, hand gestures, and body language, while conveying a message. He is also particularly observant to pitch and the tone of his voice, and he tries to receive comments and feedback from the receiver while communicating. What percentage of Henry's message is sent through nonverbal communication ?

14. 
Which one  of the following is NOT a planning process  ?

15. 
Ideally, communication between the project manager and the project team members should take place:

16. 
if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?

17. 
Effective stakeholder management includes all of the following  project elements EXCEPT:

18. 
As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer  requirements. The results should be documented and used for:

19. 
A change control board (CCB) is:

20. 
Virtual team is a tool for which of the following processes ?

21. 
Which document contains the information  that describes how the formal verification and acceptance of the project deliverables will be contained ?

22. 
Planning a project is a process that develops products such as a schedule. This process produces the following for a schedule:

23. 
In a fixed price incentive fee contract, the target cost is estimated at \$250,000 and the fee at \$35,000. The actual cost came to be \$210,000, since there was a cost saving, the seller shares the saving at a 70/30 ratio ( 70% to the buyer and 30% to the seller). What the final fee and final price ?

24. 
When a product or service completely meets customer's requirements :

25. 
Which of the following techniques is used to control the project  schedule?

26. 
When a project manager places a purchase order for a piece of equipment, it represents which of the following?

27. 
Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:

28. 
A Cost Performance Index (CPI) of 0.89 means :

29. 
Which of the following assess someone's current engagement level in a project ?

30. 
A generally accepted method to confirm accuracy of task progress is through:

31. 
In what way does free float (FF) differ from total float (TF)?

32. 
All of the following should be done during the closing process group EXCEPT :

33. 
A likely result of using "compromise" to resolve a two-party conflict is:

34. 
The objective of fast tracking a project is to:

35. 
You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making \$120,000, a 45 percent probability losing \$55,000. What does \$41,250 represent in this case ?

36. 
All the following statements about change control are incorrect, EXCEPT :

37. 
Formal written correspondence with customer is required when :

38. 
A project manager has a problem with a team member's performance. What is the BEST form of communication for addressing this problem ?

39. 
You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope.  Which document provides this information?

40. 
Which of the following is true regarding the project charter ?

41. 
Risk quantification includes:

42. 
Constructive team roles include:

43. 
While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late  finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?

44. 
What is the difference between the project plan and the performance measurement baseline?

45. 
Which of the following is output of Manage Project Knowledge process ?

46. 
A contractor's deliverable has been delayed 30 days. The process of determining how this event will affect the project schedule is called risk:

47. 
 A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?

48. 
A project's payback period ends when:

49. 
A controlling process is necessary in project management to ensure planned actions are executed and measured for progress. The controlling process for the schedule typically will focus on:

50. 
If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV) ?

51. 
During the project scope planning process, the work breakdown structure should be developed to:

52. 
Scope change control MUST be integrated with all of the following control processes EXCEPT:

53. 
Negotiating across international cultures involves mutual interdependence between parties. The negotiating MUST be conducted in

54. 
What is the MOST effective process to ensure that cultural and ethical differences do not impede success of your multi-national project?

55. 
During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?

56. 
You are asked by management to select a contract type that will obligate the seller to accept all liability for poor workmanship, engineering errors, and consequential damages in the project. Which of the following contact types will you select ?

57. 
A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is \$720,000. The planned budget for this length of the time was \$600,000. He finds that :

58. 
The primary purpose of the stakeholder register is :

59. 
To control the schedule, a project manager is reanalyzing the project to predict project  duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility.  What technique is she using ?

60. 
The disorientation experienced by people who suddenly find themselves living and working in a different environment is known as: